Matilda Bay ferry terminal contracts awarded despite local opposition

The government has signed $80.9 million in contracts to build the Matilda Bay and Applecross terminals, as the project's cost rises by about $40 million and the Minister rejects a petition signed by almost 10,000 people.

Black swans at Matilda Bay with the Perth CBD across the river, with figures: $80.9 million in contracts, about $40 million cost increase, almost 10,000 petition signatures, construction from mid-2027
Black swans at Matilda Bay. Photo: PerthNews.Co

The State Government has signed the contracts to build its Matilda Bay ferry terminal, pressing ahead with the most contested stop on its Swan River ferry expansion despite years of local opposition and a petition of almost 10,000 signatures.

Transport Minister Rita Saffioti announced on Thursday that SRG Global had won a $41 million contract to design and build new terminals at Matilda Bay and Applecross after a five-month tender. A second contract, worth $39.9 million, went to Ertech for the work on land at Matilda Bay, including charging equipment for the electric ferries, public toilets and a 48-bike shelter. Together the contracts are worth $80.9 million. Work is due to start in mid-2027.

Costs up by about $40 million

The project has also become more expensive. Ms Saffioti conceded the cost of the Metronet on the Swan ferry project had risen by about $40 million, and put it down to changes at Matilda Bay. Costs had increased "in particular for the Matilda Bay section", she said, because of changes to the design and length of the jetty.

When the Western Australian Planning Commission approved the terminals last December, the Matilda Bay stop was costed at $29.9 million.

What is being built

At Matilda Bay, the plan is a fixed jetty with a sheltered waiting area, a gangway and berths for four ferries. The government says the jetty was lengthened so the bay would not need to be dredged, and that the entrance takes up only a few metres of foreshore.

At Applecross, a smaller jetty and ferry berth will go on the north side of the Raffles complex. Existing jetties at Barrack Street will be fitted out for the new fleet of five WA-made electric ferries.

The government says it has spent the past year working with the Waterways Safety Reference Group, which represents 21 groups of river users, to design three alternative ferry routes so rowing, sailing and dinghy racing can carry on safely in the bay.

Black swans on the foreshore at Matilda Bay with the Perth CBD skyline across the river
The Matilda Bay foreshore, where the new terminal will be built. Photo: PerthNews.Co

The opposition hasn't gone away

The Matilda Bay site has been fought from the start. Hundreds of people protested at Parliament House earlier this year when a petition of more than 4,000 signatures was tabled, and the planning commission's approval last December came after a public meeting that ran for almost five hours.

Community groups Friends of Matilda Bay and Safety on Swan want the project paused. They argue the existing Nedlands Jetty, at JoJo's about 900 metres away, was never properly assessed as an alternative. They are also alarmed that the Public Transport Authority has sought an exemption to let ferries travel at up to 25 knots on stretches of river now limited to 8 knots.

"Matilda Bay is used every day by swimmers, children, rowers, sailors, paddlers, Sea Scouts and people with disabilities," spokeswoman Megan Bagworth said in October.

Nedlands MP Jonathan Huston, who left the Liberal Party in June to sit as an independent, has also opposed the terminal in Parliament. He started the Save Matilda Bay petition on Change.org, which calls for the terminal to be moved to JoJo's.

"Riddled with inaccuracies"

Ms Saffioti is not budging. Speaking on 6PR on Thursday, she said the latest petition, signed by about 10,000 people, was riddled with inaccuracies, and that the government would stick with the central Matilda Bay site because it had the least impact.

Opposition to the Applecross terminal has been more muted, although some residents have pushed for the stop to be moved across the river to Como. Bateman MLA Kim Giddens said the Applecross stop would be "a game changer" for the southern suburbs, linking residents to UWA, Matilda Bay and the city.

What happens next

Construction is due to start in mid-2027. The government's announcement didn't say when ferries would start running. When the terminals were approved last year, services were expected to begin by the end of 2027.

Sources

WA Government media statement, 26 November 2026; 6PR Mornings, 26 November 2026; The Sydney Morning Herald, 26 November 2026; ABC News, 12 December 2025; Have a Go News, 12 October 2026; WAMN News.

Get The Daily Briefing